Infor LX/BPCS Tips & Tricks for OPERATIONS: Multi-Level Shop Order Release Due Dates

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

Previous Article Infor LX/BPCS Tips & Tricks for FINANCE: Override Exchange Rate
Next Article Infor LX/BPCS -Join Us for an Exclusive Insight into Data Collection Streamlining
Print
1013 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Web Services can be very helpful for LX users to obtain updated information directly from the source, for example:

  • LX users can use a web service to request a stock check on an item for which they are going to issue a purchase order. Users can get item availability and updated pricing before placing the order.
  • LX users can also use a web service to get real time shipping charges from UPS, Fed Ex, etc. Once the user selects the appropriate freight charge, it can be added to the customer order while the order is being placed over the phone.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: At a Loss?

Loss of Key Experienced Personnel– More and more of the original “super users” have changed jobs, or retired. In their place are skilled individuals who may have been trained to execute specific tasks, but lack the experience required to respond to new and unplanned business needs and opportunities. As a result, decisions are made that may cause unintended problems. 

What is the best way to deal with this BEFORE the problem occurs? Read our blog to find out:

Read Blog

 

Optimize Your Manufacturing Today!

First96979899101103104105Last

Theme picker

Tips: LN | Baan

Instead of sharing tables through logical linking, you can replicate table content between companies. This approach allows certain non-key attributes of a record to vary by company. For example, if you replicate bills of materials rather than sharing them, each company can associate a different warehouse with the same bill of material. This way, the bills of materials are consistent across companies, while the warehouses can differ.

Replication also enables selective availability of records in other companies. For instance, when replicating items, you might limit which items are available in a sales company based on their item group, only including end items. You can further refine replication to specific subsets, such as particular item groups.

Keep in mind that replication requires any referenced tables to be either replicated or shared as well.