Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
15589 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Web Services can be very helpful for LX users to obtain updated information directly from the source, for example:

  • LX users can use a web service to request a stock check on an item for which they are going to issue a purchase order. Users can get item availability and updated pricing before placing the order.
  • LX users can also use a web service to get real time shipping charges from UPS, Fed Ex, etc. Once the user selects the appropriate freight charge, it can be added to the customer order while the order is being placed over the phone.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: At a Loss?

Loss of Key Experienced Personnel– More and more of the original “super users” have changed jobs, or retired. In their place are skilled individuals who may have been trained to execute specific tasks, but lack the experience required to respond to new and unplanned business needs and opportunities. As a result, decisions are made that may cause unintended problems. 

What is the best way to deal with this BEFORE the problem occurs? Read our blog to find out:

Read Blog

 

Optimize Your Manufacturing Today!

First9899100101103105106107Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories