Infor LN & Baan Tip: MPS planned vs. MRP planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate cumulative lead time (also called “the Critical Path”) for you.

Infor LN does not differentiate between the two. Here, it is simply an enterprise planning EP with one set of planned orders. It is possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists both in purchase and manufactured planned items. It has both non-critical and critical lead times based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V
Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN
Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Previous Article Avalara - AvaTax Integration to Infor LX, BPCS, Infor LN, Baan, and M3
Next Article Infor LN & Baan: What are your production orders telling you?
Print
30254 Rate this article:
4.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Congratulations! You bought that shiny, new car! It has all the features you can possibly want and goes a million miles an hour. It can take you anywhere your heart desires…….but you rely on a manual scooter to get you around. You know, the kind you had when you were a kid…BEFORE you could drive…before you could afford the BMW. Make sense? Uh... no.

You’d never do this, right? So, why are you doing this with the ERP system that runs your business? Why are you relying on spreadsheets and separate little Access databases to record and store the information that is the most critical to your business when you have an ERP system that is meant for this? Why continue to plod along at a snail's pace when you have the tools to take your business to the next level?

Your ERP system is your BMW. Use it. See what it can do for you. Think you’ve used it to its potential? Unlikely. We’ve helped customers breathe new life into their EXISTING ERP version all by unlocking functionality for them that was already there and ready to use! We’ve also helped by offering add-ons to the ERP that can make your productivity skyrocket.

Ask us how. We’ve got an extra set of keys to the BMW in case you lost yours.

Optimize Your Manufacturing Today!

  1. Identify the key metrics. You need benchmark data so you know what realistic goals are, then track them and publish your performance along with a brief comment from time to time on how things are trending and how you compare with others, particularly your primary competitors. The best thing about this is that it is a system that develops a life of its own.
     
  2. Measure it. Automatically, people start to think about improving things. Then the fun part, stuff begins to improve by itself. Once in place, the system just hums along and the benefits appear, because it has motivated people to think about it, and figure out what they can do to make it better.
     
  3. Communicate it. Publish your numbers, and explain to people how what they do affects the company as a whole and its success/failure. Once they see the numbers, employees quite often start to modify their behavior for the better.

Optimize Your Manufacturing Today!

First99100101102104106107108Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories