BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
39974 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

BPCS/LX Tip of the Week: CEA

CEA Upload provides the capability to prepare both Budgets and Journal Entries in Excel. Once the spreadsheet is complete, it can be uploaded to CEA for posting as an entry to the GL Book of choice. Ease of use is achieved and a full audit trail is created. LX users can capitalize on their investment in both CEA and Excel to achieve a better accounting process. 

Optimize Your Manufacturing Today!

Efficiency is something we all strive for in our personal lives and at work. How can manufacturers increase their efficiency? Take a hard look at the 4 key areas:

  1. Planning
  2. Bill of Material and Job Accuracy
  3. Inventory Planning
  4. Real Time Reporting / Processing 

Need help figuring out how to become more efficient in each of these areas? Contact us, we’d be happy to help.

Optimize Your Manufacturing Today!

First100101102103105107108109Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories