BPCS/LX Tip of the Week: Using Pre-Assigned Lot Numbers

Some items in the manufacturing process may require a lot number. A quick and easy way to release the Shop Orders with lot numbers is by using the Multi-Level Shop Order Release.

Simply select the end item from the selection screen and use action 10 for the multi-level order release. At the bottom of the release screen is the field “Pre-Assign a Lot Number to Shop Orders”. Select 1 for the pre-assigned lot number assignment option.

This option will use the pre-assigned lot number on the shop order, if the lot number exists. If the lot number does not exist, the system will automatically create a lot number and assign it to the shop order for all items that are lot-controlled.

Previous Article 4 Ways Data is Transforming Manufacturing
Next Article Eliminating Weighing Uncertainty Adds Confidence to Manufacturing Process
Print
31860 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Are your employees not as productive as you’d like them to be? Are jobs not getting completed on schedule? Without actual data, making decisions about how efficient your operation is will be difficult. Start tracking actual time to complete each operation. Compare different production lines running the same job. Is one line running more efficiently? If so, start looking at why. Track downtime, setup, etc. Once you start really analyzing each piece of the puzzle, you can begin to uncover areas that are ripe for improvement.

Optimize Your Manufacturing Today!

When there is a problem, making a decision in a vacuum is the worst thing you can do.

Get input from others within your organization. If possible, consult those at various levels. By being open with others as to the nature of the problem, and enlisting their help in determining the right solution, resistance to the recommended solution is quite often greatly reduced.

Optimize Your Manufacturing Today!

First104105106107109111112113Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories