Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In ERP LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article The Value of Upgrading Your ERP – Maintaining Modern Technology
Next Article BPCS/LX Tip of the Week: Is Lot Control Necessary?
Print
48853 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Finance: Cost Rollup by Effective Date
Allow the load standard cost from routing and cost rollup programs to process as of a specified effective date.  With the addition of an optional effective date parameter to prompt screens for cost rollup CST500 and load standards from routing CST600. If entered, only consider bill of material components and routing operations with effective and discontinue dates that make them effective as of the entered parameter effective date.


Operations: Outside Operation Purchase Order Include Vendor Item Number
Copy the vendor item number from the vendor quote to purchase orders created automatically from outside operations of shop orders. During the process of automatically creating purchase orders from outside operations of shop orders, copy the vendor item number from the vendor quote to the purchase order line. With this change, looking at a purchase order that was created automatically for an outside operation of a shop order, the vendor item number from the vendor quote will be visible on the purchase order line.


Technology: Group Security for ILM501 Inbound Delivery Maintenance
Add function key / action code security to control who is authorized to create/revise/delete functions in ILM501 Inbound Delivery Maintenance.  With added Group Security, managers can control which users are authorized to create, change and delete deliveries in ILM501 Inbound Delivery Maintenance.

First678911131415Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories