Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

Previous Article Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies
Next Article Infor LN & Baan Finance Tip: Unallocated Payment
Print
24723 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

When is the last time you took a hard look at your production lines?

  • How are we moving product through our facility?
  • Do we have work instructions / drawings available where needed?
  • Do we have frequently used inventory available at the line?
  • Where are the bottlenecks?
  • Are processes automated, where possible?

Taking a hard look at your processes and procedures may reveal some interesting results. Don’t assume that everyone is doing things the same way. Some may be superstars, and others may need some mentoring. Some processes may be outdated and costing you time and money, while others are extremely efficient. One area of the business may benefit from how others operate. Take the time to review and analyze your findings. Your company may benefit greatly as a result.

Optimize Your Manufacturing Today!

Such lofty goals you had when you implemented your ERP system. It was going to be like pressing the “Easy Button”…  then it wasn’t.

What happened? In some cases, decisions were made to implement the system “just like we used to run our old system”. Great idea? Not so much. Your business changes, and your business software needs to change as well.

Have you looked at streamlining your processes?Are you using the ERP system, but everything seems cumbersome and takes more time than its worth? Ask yourself these questions:

  • Can you automate a step or two and eliminate some manual keying?
  • Can you add barcoding to avoid keying in some information altogether?
  • How about automating the printing of some reports?

Now is the time to sit down and really review the steps required to complete the task and think out of the box a bit. Soon you can develop your own streamlined process to get the job done quickly and efficiently.

Optimize Your Manufacturing Today!

First106107108109111113114115Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories