Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

Previous Article Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies
Next Article Infor LN & Baan Finance Tip: Unallocated Payment
Print
24723 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

I hate getting lost. I feel out of control and helpless. Thank God my dad taught me early on how to read a map. Maps give us direction, points of reference, and helps us navigate the obstacles in our way.  

Do you have roadmap for your ERP system, or are you lost? An ERP roadmap can give your staff direction. It should help you create a stronger workforce that is well prepared to meet the future needs of your business. Take a hard look at what your ERP is, or isn’t doing for you. Chances are, there is much that can be done, and all you need to do is start plotting out your map. 

Optimize Your Manufacturing Today!

  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.     
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

First107108109110112114115116Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories