Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article 15 Myths About Warehouse Automation
Next Article BPCS/LX Tip of the Week: Establish Costing For Purchased Items
Print
46339 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

  • Print Sales Order History Information - all invoices processed through sales
  • Check Inventory Valuation - this should tie out to your inventory accounts
  • Print Integration Information - see all postings from WIP to finished goods
  • Print G/L Transaction Information - print specific transaction types for any GL account
  • Print Lot Control Information - will show where serial numbers were used

Optimize Your Manufacturing Today!

Standard costing is really a ‘best guess’ at labor costing -- these numbers are often inaccurate, incomplete or out of date.

Accurate job costing requires the capture of all tasks associated with a specific product or job, including direct and indirect labor in setup, production, and customer service.

Inaccuracies in the collection of time allocated to machinery and the use of materials can result in the inability to properly pass those charges through to the customer, reducing company profitability.

Basically, you can’t manage what you can’t measure -- and you can’t measure what you can’t track. So the inability to track time-to task ultimately inhibits maximum utilization of the workforce. Unproductive activities remain hidden from sight -- managers don’t have the information needed to understand where wasted time exists, and therefore cannot create an action plan to remove it.

Optimize Your Manufacturing Today!

First110111112113115117118119Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories