Kathy Barthelt

Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan TECHNOLOGY Tip: Are you running the latest Infor components?
Next Article Infor LX / BPCS Tips & Tricks for EXECUTIVES
Print
17640 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

  • Sit down with your IT team. Decide how the information will be captured and where it will be stored so that employees have access to it. What software tools need to be used to capture the information? How does it need to be organized? Create a repeatable process to make this easy for your staff.
     
  • Interview the person. Have them talk you through his/her job. What are the things they do every day? What are their biggest challenges? How do they overcome them? 
     
  • Have someone shadow the person for a week. Watch what they do and how they do it. Ask questions. Who does he/she interact with in their department? Outside of their department? Why?
     
  • Find out what tools he/she uses to perform their job? Are there spreadsheets?  Reports within your ERP / outside of your ERP? Separate stand-alone databases? Drawings? Websites? Why does he/she use them?
     
  • Video record how the person does their job. Is their technique critical to “doing it right” the first time and not ending up with a bunch of scrap that you can’t reuse?
     
  • Figure out if the person does anything special on a monthly, quarterly, or annual basis that might not come up during the observation period or interview. 
     
  • Map how he/she uses your business system and how that impacts the rest of the company. Understand both the “what” and the “why”. Without this, new employees may end up figuring out what they need to do, but never understand why they need to do it.

Optimize Your Manufacturing Today!

  • Are you tracking downtime? Is it done manually, or with some type of automation or application that gathers information in real-time, or is it based upon history?
  • If you are measuring team effectiveness by shift, you know there are significant differences between them. Have you figured out why?

One of our automotive customers was experiencing significant inefficiencies and difficulties with their receiving operations. After analyzing their operation, we discovered a disconnect between how they were tracking their incoming goods and what their ERP system thought was on hand.

This disconnect created time-consuming steps to process incoming material and determine where the material was needed. The manual process slowed production, caused additional staffing needs and hindered their ability to effectively get needed material to the assembly line. They chose to implement our data collection solution to automate the process.

Since implementing the solution, receiving and moving material was quicker, more accurate and efficient. This enabled the addition of another assembly line, increasing production volume – without adding staff.

Optimize Your Manufacturing Today!

First111112113114116118119120Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories