BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
39844 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

  • In Infor LX you need to determine how inventory will be moved in and out of warehouse storage locations, and which of the following transactions to use for inventory control:
  • A transfer transaction can be used to move inventory from one warehouse location to another warehouse location.
  • A production receipt transaction is used to add inventory to a warehouse location.
  • A material issue or backflush is used to reduce inventory from a warehouse location.

Two big sources of inefficiencies in manufacturing are paper and spreadsheets. I know that you love ‘em, but they are the cause of more problems than you probably realize. Think of how long it takes you to get paper based data into the hands of those who can do something valuable with the data. Are you capturing all of the information correctly? Timely? What about those spreadsheets? Can everyone access that information across your organization? Is that data married with all of the related data regarding your operations to give your executive and middle management the information they need when they need it?

Make your shop floor paperless and put in place systems that talk to one another and automatically pull and push data to and from your ERP so that you can look in one place for all the information you need to run your business effectively.

If you’re not doing this today, you might as well be burning money.

First118119120121123125126127Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: