Infor LN & Baan Tip: Remove Posted Payment/Direct Debit Batches

The functionality of session Remove Posted payment batches tfcmg1259m000 and Remove posted Direct Debit batches tfcmg4259m000 is explained below:

1.These 2 sessions can be used to removed already posted payment/direct debit batches that have been processed through CMG Module. After the batches are changed to removed status they can be deleted also.

2. Only a superuser, defined in the Payment Authorizations (tfcmg1100m000) can delete the payment/direct debit batch.

3. A payment/direct debit batch once removed cannot be retrieved. The data gets removed only from payment advice tfcmg1609m000/direct debit batch tfcmg4609m000 and composed payments/direct debits.

4. The details of the invoices that were selected in the removed payment/direct debit batch can be seen in session anticipated payment/receipt tfcmg2504m000 and from here you go into the anticipated document details to see the list of invoices selected.

5. Remove payment batches does not impact the check master and the check details remain in the check master. 

6. The anticipated receipt/payment document can be reconciled as usual following the receipt/payment reconciliation process.

7. The anticipated payment/receipt document details are not removed from GLD and ACR sessions or tables and can be seen in document history and ACP/ACR open entries.

8. The direct debit batch number can be retrieved from session tfacr6500m000(receipt related document). And the payment advice batch number can be retrieved from payment-related document tfacp6500m000 or the check master if the payment has been done through checks.

Previous Article Understanding Taxability Rules Is Key To Sales Tax Compliance
Next Article Infor LX & BPCS Manufacturing Tip: Production Register Listing
Print
26066 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding: How many hours remain in total and at each operation?

First let’s look at some key BPCS Master File data starting with the routing file.

How many routing steps (operations) are set up that reflect how the product is produced in the factory? If you take a short cut and set up only one operation for the entire process, then you will limit the information seen on the SO inquiry program. Set up the operation steps to reflect what you want to report back to from the factory floor.

Will each of the routing steps run in one work center, or in different work centers? To keep it simple you may want to set up work centers as departments. For example:

  • Assembly
  • Machine
  • Paint
  • Etc.

For each operation setup consider how you have set up the following:

  • Load Codes – for example a code 5 is used if reporting both setup time and run labor time. These codes are maintained in the work center file
  • Basis Code – typical codes are P for pieces per hour,  3 is used for hours per 1,000 pieces
  • Setup hours – if you set them up, you also want to report them
  • Run hours – Direct Labor
  • Machine hours

How you set up th

Came across an article online from Lauber CFO’s, and thought I would share. Here is a checklist for things to consider in order to finish out the year and help you plan for 2016:

 

  • Are your accounting records up to date so that you can make a projection of how the current year will turn out?
  • Are all account reconciliations currently up to date to facilitate the closing of the books after year end?
  • Are there accounts receivable that should be reserved for or written off prior to the end of the year?
  • If your business carries inventory, do you need to plan a physical count as of the end of the year?
  • Has depreciation on your fixed assets been recorded during the year? Have you considered depreciation on current year additions?
  • Have all new asset purchases and bank loans been recorded on your books?
  • Are there any liabilities, for example, pending legal actions or warranty issues, which will need to be recorded prior to year end? 
  • Do you have a plan in place to properly “cut-off” revenue at year end to properly match revenue and expense?
  • Will there be bonuses, profit sharing contributions or discretionary retirement plan contributions paid prior to the end of the year? How will these payments affect cash f
First119120121122124126127128Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...