Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Anthony Etzel
/ Categories: ERP News, Event / News

Why should you look at OTTO? Let’s see what an OTTO customer has to say:

"When first introduced to OTTO, for on-time ordering, you could not prove to me that there was a better system out there than what we already had. Boy what a big wakeup call! Being in a very option intensive business and the economy in a very flat or negative state, OTTO is the BEST tool to quickly respond to a customer’s needs TODAY. When Millions of dollars are at stake each month, we have to be better prepared to meet the task at hand with fewer people. OTTO is really doing this for us!  What normally took us hours or days to identify several indented bill of material shortages now only takes a few moments with the OTTO program. What this really means is that, we do not have to wait for MRP to run each week to plan and reschedule orders. This can be done today!  What I’m really saying is that, we can advise Purchasing and Scheduling TODAY without waiting for TOMORROW.  We are now able to ship DOLLARS this month and satisfy our CUSTOMERS. Without OTTO in some cases, the Customer would have to wait until next month and potential revenue dollars lost for the month."  Gary Hawk, Planning Manager - construction equipment

Previous Article Infor LX / BPCS Tip of the Week: Control Date Lead Times in LX
Next Article Crossroads RMC Forms Strategic Partnership with CTN Global
Print
27983 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In LX, the actual costs that can be set up fall into three categories: Material, Labor, and Overhead. If your LX database is set up properly with the LX cost accounting, you should be able to identify:

  • How much the item should cost
  • How to track the cost of work underway
  • How much the item actually did cost
  • Why the job cost varied from the expected cost
     

Capturing the data to track activity with associated costs can be time-consuming. With an MES solution, the information you need for costing is tracked instantly.

First120121122123125127128129Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories