Infor LN & Baan Tip of the Week: The Production Bill of Material – 10.7

The production bill of material is globally specified at the company level. It can be used as a source for the definition of the local material lists, such as:

  • The production model in the repetitive module.
  • The production model in the job shop module.
  • The subcontracting model in the subcontracting module.

The production bill of material can be generated through the engineering bill of material. The new production bill of material differs from the old bill of material:

  • It has a header and a status.
  • It is always revision controlled.
  • The effective dates have been moved from the material lines to the header.
  • The BOM quantity has been moved from item production data to the header.
  • The use up has been moved from alternatives to the material line.
  • The material line excludes logistic data (no warehouse nor routing operation).

The production bill of material is not mandatory.

Production bill of material revisions:
The production bill of material is revision controlled. The objective of the revision is to control the changes to the bill of material over time.

The P-bom includes this revision-related data:

  • Revision number
  • Effective date and Expiry date
  • Status (New, Approved, Expired)
  • Creation date and Created by: user
  • Approval date and Approved by: user
  • Expiry date and Expired by: user
  • Source information
Previous Article IDF News: Importing LX Security into IDF
Next Article Hunter Douglas Architectural Products Selects Crossroads RMC for LN 10.6 Upgrade Project
Print
40896 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Understanding: What Was Issued to the Shop Order

The shop order inquiry program provides several function keys. By using the function key for the material, the display will present what components have been issued under the issued quantity column. You are also presented with the required quantity. While viewing the quantities you may see that more was issued than what was required. Possibly there was scrap and more material was required to be issued. Perhaps there was an over issue and the balance of the material is slated to be returned to stock.

A red flag should go up if the Shop Order quantity finished is equal to the required quantity for the end item and all the components have not been issued. You may want to investigate why.

First121122123124126128129130Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: