Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)

When the Generate Order Planning (cprrp1210m000) session is run it can take minutes to days to finish the process.

The performance of this session depends on many settings, like the number of plan items, the number of orders, but it also depends on hardware and database setup.

Here are some guidelines on how performance can be improved.

  • Be sure you are always on the latest solutions with the planning sessions. We are constantly improving the software to gain more speed in the Enterprise Planning (EP) sessions.
  • The number of planned items is critical. Try to reduce the number of planned items. Is it necessary that all items be planned via EP? For shop floor stock the TPOP or SIC replenish systems are often more suitable.
  • When you use PCS, be sure to close the projects when they are finished. When a PCS project has status Closed, the customized items will not be planned.

It's better to run Remove Plan Items for closed Projects (cprpd1220m000). This session removes the item planning data for customized items of closed projects.

  • If you run EP with the option, Also Generate Item Master Plan and/or Online Update Item Master Plan, consider if you need an Item Master Plan for all plan items. An Item Master Plan is usually meant for global long-term planning. Again this is not very useful for shop floor stock. Reducing the number of master-planned items improves performance.
  • When you use Resource Master Plans; are all your resources really critical? If a work center is not critical do not create a Resource Master Plan for it.
  • When using Item Master Plans and/or Resource Master Plans, set in Scenarios (cprpd4100m000) the total scenario length as short as possible. For example, if your sales order horizon is 2 years, a scenario end date which is 3 years after the current date is sufficient. During the calculations of the Item Master Plan and the Resource Master, all periods defined in the scenario are checked and calculated. So if you have the end date of the scenario on 2038, EP will do the calculations (for every master-planned item) until 2038.

Defining a rolling scenario will keep your scenario length constant and you don’t have to worry that you run beyond your scenario's end date.

  • Updating the pegging relations has a serious impact on the EP performance. In EP Parameters (cprpd0100m000) you can set the Pegging Horizon in days. Keep this horizon as short as possible. The Update Signals by Item/Planner option also has some impact, but less than the pegging.
  • EP uses the so-called phase numbers to detect the lowest level in which an item is used within a BOM structure or in a supplying relation. If the phase numbers are not ‘up-to-date’, EP will correct the phase numbers during the planning. This takes time during the planning run. If there are loops in BOMs or in supplying relations, this recalculation has a big impact on the performance. Therefore you could run Compute Phase Numbers (cprpd6200m000) on a regular basis. For example once a month. Always run this session with the Generate Report option selected. If loops are detected these are reported. Be sure to solve all the reported errors.
  • When unexpected results occur, especially when the data is imported from external packages, always check the number of records in tables cprpd100 and cprpd120. The number of records should match! Remark: From 10.4 onwards the table cprpd120 has become obsolete so this point not applicable anymore.
  • The number of calendars also impacts planning performance. Then for every warehouse, work center, or BP, and so on, a different calendar is defined. Planning has to read all of these calendars from start to end. This can have a huge impact on performance.
    • If you link a calendar to a work center or warehouse, avoid defining a new calendar for every work center/warehouse. Try to link the same calendar to more than one department.
    • Define the start of the calendar close to the start date of the scenario. For example, the current date is 01-07-2014, the start date of the scenario is 365 days in the past. So a start date for your calendar could be 01-07-2012.
    • Define the end date of the calendar not too far in the future. Depending on the end date of the scenario you could use 5 years ahead.  For example, the current date is 01-07-2014, the end date of the scenario is 3 years in the future. So an end date for your calendar could be 01-07-2022. Do not define an end date past 19-01-2038, which is the last UTC date Infor LN can handle.

Also, the interaction with the database can have a big impact on performance. 
A commonly used way to improve the total run time of the EP run is to start the session in parallel processing. 
See also Knowledge Base Article 22881401 Performance, Tracing and tuning Guide, for more details.

These guidelines are just some hints, and a good starting point because performance is a complex issue.

Previous Article Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1
Next Article Infor LX & BPCS Finance Tip of the Week: Invoice Level Inquiries – ACR300D7
Print
28444 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Understanding: How many hours remain in total and at each operation?

Now let’s look at what information is being supplied from the shop floor.

It’s not uncommon for transaction reporting to be captured manually on the shop packet that was issued to the factory floor when the SO was released.

The big question is, is anything done with the data? Is it collected and keyed to a  spreadsheet and not shared, or is the transaction data keyed to SFC600? If it is being keyed, ask how often and by whom? Some companies use alternative methods to capture transaction data that do not require batch keying via a keyboard.

Not a lot of data is required to be keyed to SFC600 in order for the SO Inquiry to be useful. The data that should be reported for the transaction process is as follows:

  • The type of hours being reported – machine, run labor, setup labor
  • If reporting setup and run labor you want an employee clock number
  • The shop order and the operation that is being reported
  • Is the operation complete
  • How many good were produced at this operation
  • How many hours – the numbers of hours are critical. Do the employees estimate how many hours they worked, or do they track actual time started and stopped in order to calculate the actual number of hours.

Based on what is captured and how often will have an impact on the SO inquiry screen. Understanding the batch times as to when the transactions are keyed will provide you with the window as to the SO status at that point in time. Or, are they keyed as they happen in a near real time fashion so that you can have a more current view of the factory floor.

First122123124125127129130131Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: