Infor LN & Baan Tip of the Week: The Production Bill of Material – 10.7

The production bill of material is globally specified at the company level. It can be used as a source for the definition of the local material lists, such as:

  • The production model in the repetitive module.
  • The production model in the job shop module.
  • The subcontracting model in the subcontracting module.

The production bill of material can be generated through the engineering bill of material. The new production bill of material differs from the old bill of material:

  • It has a header and a status.
  • It is always revision controlled.
  • The effective dates have been moved from the material lines to the header.
  • The BOM quantity has been moved from item production data to the header.
  • The use up has been moved from alternatives to the material line.
  • The material line excludes logistic data (no warehouse nor routing operation).

The production bill of material is not mandatory.

Production bill of material revisions:
The production bill of material is revision controlled. The objective of the revision is to control the changes to the bill of material over time.

The P-bom includes this revision-related data:

  • Revision number
  • Effective date and Expiry date
  • Status (New, Approved, Expired)
  • Creation date and Created by: user
  • Approval date and Approved by: user
  • Expiry date and Expired by: user
  • Source information
Previous Article IDF News: Importing LX Security into IDF
Next Article Hunter Douglas Architectural Products Selects Crossroads RMC for LN 10.6 Upgrade Project
Print
40896 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Understanding: How many hours remain in total and at each operation?

Now let’s look at what information is being supplied from the shop floor.

It’s not uncommon for transaction reporting to be captured manually on the shop packet that was issued to the factory floor when the SO was released.

The big question is, is anything done with the data? Is it collected and keyed to a  spreadsheet and not shared, or is the transaction data keyed to SFC600? If it is being keyed, ask how often and by whom? Some companies use alternative methods to capture transaction data that do not require batch keying via a keyboard.

Not a lot of data is required to be keyed to SFC600 in order for the SO Inquiry to be useful. The data that should be reported for the transaction process is as follows:

  • The type of hours being reported – machine, run labor, setup labor
  • If reporting setup and run labor you want an employee clock number
  • The shop order and the operation that is being reported
  • Is the operation complete
  • How many good were produced at this operation
  • How many hours – the numbers of hours are critical. Do the employees estimate how many hours they worked, or do they track actual time started and stopped in order to calculate the actual number of hours.

Based on what is captured and how often will have an impact on the SO inquiry screen. Understanding the batch times as to when the transactions are keyed will provide you with the window as to the SO status at that point in time. Or, are they keyed as they happen in a near real time fashion so that you can have a more current view of the factory floor.

First122123124125127129130131Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: