BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
39844 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding: How many hours remain in total and at each operation?

First let’s look at some key BPCS Master File data starting with the routing file.

How many routing steps (operations) are set up that reflect how the product is produced in the factory? If you take a short cut and set up only one operation for the entire process, then you will limit the information seen on the SO inquiry program. Set up the operation steps to reflect what you want to report back to from the factory floor.

Will each of the routing steps run in one work center, or in different work centers? To keep it simple you may want to set up work centers as departments. For example:

  • Assembly
  • Machine
  • Paint
  • Etc.

For each operation setup consider how you have set up the following:

  • Load Codes – for example a code 5 is used if reporting both setup time and run labor time. These codes are maintained in the work center file
  • Basis Code – typical codes are P for pieces per hour,  3 is used for hours per 1,000 pieces
  • Setup hours – if you set them up, you also want to report them
  • Run hours – Direct Labor
  • Machine hours

How you set up th

Came across an article online from Lauber CFO’s, and thought I would share. Here is a checklist for things to consider in order to finish out the year and help you plan for 2016:

 

  • Are your accounting records up to date so that you can make a projection of how the current year will turn out?
  • Are all account reconciliations currently up to date to facilitate the closing of the books after year end?
  • Are there accounts receivable that should be reserved for or written off prior to the end of the year?
  • If your business carries inventory, do you need to plan a physical count as of the end of the year?
  • Has depreciation on your fixed assets been recorded during the year? Have you considered depreciation on current year additions?
  • Have all new asset purchases and bank loans been recorded on your books?
  • Are there any liabilities, for example, pending legal actions or warranty issues, which will need to be recorded prior to year end? 
  • Do you have a plan in place to properly “cut-off” revenue at year end to properly match revenue and expense?
  • Will there be bonuses, profit sharing contributions or discretionary retirement plan contributions paid prior to the end of the year? How will these payments affect cash f
First123124125126128130131132Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: