Infor LX & BPCS Manufacturing Tip: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days. Backward Scheduling Process The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.

2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours

3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100

4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.

5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Backward scheduling is supported in all shop order release programs (SFC500, SFC550, and FAS510). Backward scheduling is recalculated if a shop order is maintained through SFC500 when the due date or the required quantity is changed; however, you cannot enter move and queue times through the maintenance program when adding an operation to the shop order.

Previous Article Infor LX & BPCS Tip: What is IDF and how could it make my life easier?
Next Article Infor LN & Baan Manufacturing Tip: All About Routings
Print
19461 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Some items in the manufacturing process may require a lot number. A quick and easy way to release the Shop Orders with lot numbers is by using the Multi-Level Shop Order Release.

Simply select the end item from the selection screen and use action 10 for the multi-level order release. At the bottom of the release screen is the field “Pre-Assign a Lot Number to Shop Orders”. Select 1 for the pre-assigned lot number assignment option.

This option will use the pre-assigned lot number on the shop order, if the lot number exists. If the lot number does not exist, the system will automatically create a lot number and assign it to the shop order for all items that are lot-controlled.

Just a refresher on a tip I’ve shared previously from supply Chain Technology Bulletin regarding how to attain greater inventory accuracy. I thought it would be worthwhile to share again:

  1. Record data regarding your inventory as soon as the items arrive at your door / receiving dock. With information, you can make decisions. Without it, you waste money, time, and effort.
  2. Leverage data collection, label generation, and RFID solutions to make your life easier.
  3. Set inventory accuracy goals for the business and for employees.
  4. Train your employees so they know what is expected of them, and how to best perform their job and therefore how best to maintain accurate inventory counts.
  5. Count the inventory – and do it regularly. Find a method that works best for your employees, and for your business.
First124125126127129131132133Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories