Infor LX / BPCS Tips & Tricks for EXECUTIVES

FINANCE: Prevent Voiding of Selected Invoices
This enhancement prevents users from voiding invoices after they have been selected for payment. If a user selects an invoice for payment and another user voids the invoice during the payment process, it can produce erroneous and duplicate records. The ACP500 programs were modified to check the status of an invoice before it can be voided. If the invoice has been selected for payment, a message is generated, and the invoice cannot be voided.

OPERATIONS: Copy Shop Order
In the Shop Order Selection program, action 3=Copy is available. This action allows copying any shop order except for flow orders or campaign orders. Instead of copying from the parent item's bill of material and routing, the new shop order’s materials and operations will be copied from the selected shop order. Note that if the existing shop order is linked to a customer order or line, this linkage will not be copied to the new shop order.

TECHNOLOGY: Group Security for ILM501 Inbound Delivery Maintenance
Add function key / action code security to control who is authorized to create/revise/delete functions in ILM501 Inbound Delivery Maintenance.  With added Group Security, managers can control which users are authorized to create, change and delete deliveries in ILM501 Inbound Delivery Maintenance.

Previous Article Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned
Next Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Print
4174 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

First124125126127129131132133Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...