Baan/LN Tip of the Week: Differences Between Constraint Planning in Baan IV and Enterprise Planning in LN

In Baan IV, a distinction is made between the actual ERP system and a separate planning tool which contains the Constraint Planning package. This tool was intended to work with any ERP system, not just with Baan IV. The Enterprise Planning package is now considered to be a package like any other package in Infor LN.

Users of Baan IV could choose whether they wanted to plan their supply in one of the following ways:

  • By using the MPS and MRP modules in the Manufacturing package.
  • By using the RPD and RMP modules in the Constraint Planning package.

Users of Infor LN can only use the Enterprise Planning package. The distinction between the MPS items and MRP items has been abandoned. In Infor LN, all items can be planned by using a combination of master-based planning methods and order-based planning methods.

Previous Article Strategy, Not Technology Drive Digital Transformation
Next Article BPCS/LX Tip of the Week: Indirect Time Reporting
Print
47152 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Get ahead of the curve with a seamless, comprehensive integration strategy that surpasses other competitive solutions. In part two of this webinar, join our discussion of best practice integration tricks and solutions from a fellow customer’s office of finance. Understand what makes their integration approach effective and review best practices in integrating your IBM i solution to other office of finance solutions (F9/EPM/Birst/GRC).

Hosted by Peg Tuttle from the IBM i podcast, “The Incredible i Show”. 

  • How version upgrades have tightened internal control loopholes.
  • Structural IBM i advancements designed to safeguard your organization.
  • IBM i ecosystem solutions that strengthen both data and access vulnerabilities.

Don't miss this fourth fireside chat, Eight Ways to Modernize your IBM i product – Topic #3 of 8: Best practices in integration for the office of finance (Part 2). Register today!

Register today!

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

First89101113151617Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories