Infor LX/BPCS Tips & Tricks for OPERATIONS: Shelf Life Days and Retest Days

This feature provides the ability to enter information in the shelf life days and retest days fields for non-QMS lot controlled items, even when the QMS product is installed. The purpose of this enhancement is to allow the user to enter information for non-QMS lot controlled items even when QMS is activated in Parameters Generation, SYS800D.

In previous versions, when QMS was activated, the Shelf Life Days and Retest Days fields in Facility Planning Maintenance (MRP140) and Item Master Maintenance (INV100) were not maintainable for non-QMS lot controlled items.

Previous Article Infor News You Can Use | Why Upgrade to Infor LX in the Cloud
Next Article Infor LX/BPCS Tips & Tricks for EXECUTIVES
Print
837 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.

  • If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  • If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

First125126127128130132133134Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...