Infor LX & BPCS Tip: Capacity Planning – Resource Requirements Reports

Resource Requirements Report (CAP260D) generates five capacity reports:

  • Labor Resource Requirements
  • Machine Resource Requirements
  • Setup Resource Requirements
  • Setup and Labor Requirements
  • Setup and Machine Requirements

The Labor Resource Requirement report lists requirements that are calculated from the run hours on each routing and the MRP/MPS demand in the Capacity Requirements Detail File (LCR). The calculation does not consider crew size.

The Machine Resource Requirement report lists machine hour requirements based on routings and the MRP/MPS demand in the Capacity Requirements Detail File (LCR).

The Setup Resource Requirements report lists setup labor requirements based on routings and the MRP/MPS demand in the Capacity Requirements Detail File (LCR).

The last two reports combine setup hours with labor hours and setup hours with machine hours to provide two separate reports that summarize the requirements by work center with totals by department. The system computes requirements similarly to the way it computes them on the other reports.

Have questions on this process or need some help? Contact us! Our experienced consultants will be glad to assist you.

800.762.2077

Previous Article 6 Ways Disconnected Data is Harming Your Business
Next Article Infor LN & Baan Tip: What is the GRNI Reconciliation Process?
Print
10100 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

First127128129130132134135136Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last