Kathy Barthelt
/ Categories: Event / News

Crossroads is proud to work with Johnson Crushers International on their LN re-implementation to 10.6

Johnson Crushers International (JCI), a global leader in engineering and manufacturing full lines of cone crushers, horizontal and incline vibrating screens and track-mounted, portable and stationary crushing and screening plants, has selected Crossroads RMC to help them re-implement Infor LN on 10.6.  JCI’s main objectives with this project are to support their continued growth, align and standardize their business processes, and enable a continuous improvement effort to drive additional value to the business. Go live is expected to occur in early Q1 of 2020.

Previous Article Baan/LN Tip of the Week: Warehouse Material Movement / Problems With the Inventory Structure Table (whinr150)
Next Article Nazdaq has released Version 3.0 of B2Win Suite
Print
14731 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

First128129130131133135136137Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last