OPERATIONS: Order Quantity Dependent Routings vs Default Routings
Order quantity-dependent routings
An automatically selected routing tailored to a specific production order quantity is useful. An example would be if the production order quantity is large, a routing with high production rates is used; If the order quantity is small, another routing is selected.

You can set up these quantity-dependent routings:

  • Select the Quantity-dependent Routing check box in the Item - Production (tiipd0101m000) session.

  • Enter the routing codes in the Item - Routings (tirou1101m000) session. Enter the maximum quantity for which a routing is valid in the Up to Quantity field.

Note: If multisite functionality is activated, the routings available may vary per site on the job shop bill of material selected. Differences in routings have an impact on the standard cost calculation.

Default routing

If the Quantity-dependent Routing check box is not selected, the default routing applies to an item. However, this default routing must also be linked to the item. To find out, LN checks the default routing code in the Default Routing field of the Job Shop Master Data Parameters (tirou0100m000) session. Next, LN checks whether the default routing code is linked to the item in the Item - Routings (tirou1101m000) session. If so, the default routing applies to the item. If the default routing is not linked to the item, no routing is used.


FINANCE: Integration Transactions - Compression
Integration transactions can be compressed before they are posted. For each integration document type, you can indicate whether the debit transactions and/or the credit transactions must be compressed.

Transactions can be compressed if the following transaction details have the same value:

  • The source financial company.

  • The destination financial company.

  • The transaction type and series.

  • The ledger account and dimensions.

  • The transaction currency.

  • The fiscal year and the financial period, the tax period, and the reporting period.

  • The integration document type and the Debit/Credit indicator.

  • If related gain and loss transactions are generated, the same compression criteria are used to compress these.

Note: Intergroup transactions are not compressed.

 
TECHNOLOGY: Infor LN Rest API

Frequently Asked Questions (KB2316174)

For Infor LN a framework has been developed to support REST API-based services for lean integrations. This framework is now made available for the LN application. This KB answers some common questions you may have and procedures that are needed for using the LN Rest APIs.

More details on these topics can be found in the Infor LN REST API Administration Guide.

Previous Article Infor News You Can Use: Discover the Power of Advanced Planning & Scheduling with industry expert Greg Keating
Next Article Infor News You Can Use | Why Upgrade to Infor LX in the Cloud
Print
2833 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

â–ª Four sets of costs: actual, standard, frozen standard, and simulated

â–ª Nine user-defined elements per set

â–ª Full and partial cost roll-up and simulation

â–ª Cumulative in-process cost tracking

â–ª Cost summaries by item

â–ª Cost definition tied to work centers or material type

â–ª Process hour costing

First129130131132134136137138Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...