How to Improve Customer Shipments With OTTO - A Case Study

Setting Industry Service Standards

Shenandoah Manufacturing, a $20 million producer of poultry-raising equipment (heaters and brooders), had been having difficulty for some time shipping orders to customers in a timely manner. They had successfully implemented a popular ERP system and had been using it for more than 3 years, yet the situation didn't improve. 

Customer Service Representatives were complaining about the frequent backorders and late orders. Employees were giving it their best effort, but were frustrated, and customers were threatening to take their business elsewhere.

The company considered installing an APS system as a possible solution, but found implementation would be difficult, expensive, and running the system might be a challenging task as a number of key business practices would have to be changed. A consultant familiar with OTTO suggested they look at that product as an alternative to APS. Several OTTO aspects cited by the consultant convinced them to consider a cursorily review. Specifically:

  • The non-intrusive nature of the product.
  • It's relative inexpensive initial investment.
  • The low overall total cost of ownership.
  • The integration with their ERP system.

The initial demonstration was impressive. OTTO was installed on Shenandoah's server within 45 minutes of arrival and, most impressively, it was fully functional with their real “live” data immediately. Needless to say, the demo was well received. Even more importantly Shenandoah was able to “test drive” the software to prove its applicability before making any dollar commitments.

According to Mark Shank, Information Systems Manager, some baseline measurements were made last year, and it was determined that approximately 50% of their customer orders had shipped on time. As they began using OTTO, on-time order performance rose to 90% for the month. And Shenandoah caught up on its entire backlog and started working ahead on February's orders. In February on-time shipment performance jumped to 92% and subsequently on-time performance has ranged somewhere between 98.3% and 99.5% — well above the 96% goal set by Management.

OTTO provides the means for keeping the whole production organization focused on the few things that have to happen as the ship date approaches to get each order shipped on time. Components that have the potential for delaying an order are identified so they can be managed. Shenandoah's staff, a precious and limited resource, now concentrates on analyzing information and managing the right things at the right time rather than digging out date. To quote one production control individual: “what use to take hours now takes seconds.”

According to Roy Hackett, Plant Manager: "Knowing the right things to pay attention to at the right time — information provided by OTTO — has allowed on-time shipping to be improved by 40 percentage points in less than one month and a lead time reduction from 3-4 weeks to 1-2 weeks on the most important products"

Guessing at what and how much of the work being processed is for real customer orders versus planned orders is eliminated which is especially important when capacity is short during the heavy portion of the business cycle. 

“By focusing on the right things at the right time, production expedites and interruptions are far fewer, production flow is much smoother and productivity is significantly improved.”

Previous Article Crossroads RMC's Analytics Dashboard serves as the perfect complement to extend your MES solution
Next Article Steps to undo an IDF modification and restore to the default
Print
22703 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

â–ª Four sets of costs: actual, standard, frozen standard, and simulated

â–ª Nine user-defined elements per set

â–ª Full and partial cost roll-up and simulation

â–ª Cumulative in-process cost tracking

â–ª Cost summaries by item

â–ª Cost definition tied to work centers or material type

â–ª Process hour costing

First129130131132134136137138Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...