Baan/LN Tip of the Week: Warehouse Material Movement / Problems With the Inventory Structure Table (whinr150)

This has come up as an issue during various stages of warehouse material movements – transfers, outbounds, shipments. We have seen it right up to 10.4. The inventory structure table (whinr150) becomes a problem. The error points to that table, but users are lost as to how to fix it.

In the session Units by Unit Set many companies let the field Storage default to Yes. If the UOM is not intended to be used in inventory then that setting should be No. 

If an item is purchased in UOM different from the inventory unit and the setting is Yes then LN adds a record in that UOM to the inventory structure table. It is that record that causes problem later.

The session has an option to change the value of the storage field. Specific > Convert Use for Storage. This option works both ways and will correct all inventory in the UOM range. 

Should a user receive an error that references inventory structure table then the solution is to check that session to see if an odd UOM exists in it. If so use the Convert Use for Storage to correct the problem.

Previous Article Baan/LN Tip: Disabling Unused Functionality in LN
Next Article Crossroads is proud to work with Johnson Crushers International on their LN re-implementation to 10.6
Print
36576 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

▪ Four sets of costs: actual, standard, frozen standard, and simulated

▪ Nine user-defined elements per set

▪ Full and partial cost roll-up and simulation

▪ Cumulative in-process cost tracking

▪ Cost summaries by item

▪ Cost definition tied to work centers or material type

▪ Process hour costing

First129130131132134136137138Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...

12345678910Last