BPCS/LX Tip of the Week: Indirect Labor Reporting

In the Shop Floor Control Module, you have the ability to key in both direct labor and indirect labor. However you want to establish specific types (reasons) for the indirect labor. The SFC600 labor entry program shows a reason code field, but it is designed for reject quantity and machine downtime reasons, not indirect labor reasons.

There is a way around this. With an MES solution you have the ability to setup and report indirect time against a specific reason code.
Previous Article Baan/LN Tip of the Week: Configuring Items in Infor LN
Next Article Why Your Operation Doesn’t Stand a Chance in Hell of Going From Good to Great (and What to do About it)
Print
52568 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

â–ª Four sets of costs: actual, standard, frozen standard, and simulated

â–ª Nine user-defined elements per set

â–ª Full and partial cost roll-up and simulation

â–ª Cumulative in-process cost tracking

â–ª Cost summaries by item

â–ª Cost definition tied to work centers or material type

â–ª Process hour costing

First133134135136138140141142Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)