Infor LN & Baan Tip: MPS planned vs. MRP planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate cumulative lead time (also called “the Critical Path”) for you.

Infor LN does not differentiate between the two. Here, it is simply an enterprise planning EP with one set of planned orders. It is possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists both in purchase and manufactured planned items. It has both non-critical and critical lead times based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V
Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN
Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Previous Article Avalara - AvaTax Integration to Infor LX, BPCS, Infor LN, Baan, and M3
Next Article Infor LN & Baan: What are your production orders telling you?
Print
30254 Rate this article:
4.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

â–Ş Four sets of costs: actual, standard, frozen standard, and simulated

â–Ş Nine user-defined elements per set

â–Ş Full and partial cost roll-up and simulation

â–Ş Cumulative in-process cost tracking

â–Ş Cost summaries by item

â–Ş Cost definition tied to work centers or material type

â–Ş Process hour costing

First133134135136138140141142Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories