Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Crossroads RMC

Infor OS Webinar: Developing ION API Authorized Applications Webinar – October 2, 2019

Do you want to consume ION APIs but are confused by API security?

Do terms like authorization, consent, resource owner, authorized application, OAuth2 grants, tokens, and service account sound alien?

If you answered “yes” to any of these questions, join this free webinar to learn about these concepts and become a champion API consumer.

During this webinar, you will learn about: 

  • ION API Overview
  • API Security with OAuth2
  • Choosing OAuth2 grant
  • OAuth2 grant details
  • Reference Implementations and best practices
  • Q&A

Register CLOSED

Previous Article IDF News: default order class for the warehouse customer
Next Article Infor LN & Baan Tip of the Week: Job Shop Bill of Material – 10.7
Print
32970 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.
First133134135136138140141142Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...

12345678910Last

Theme picker

Categories