Infor LN & Baan Tip of the Week: Job Groups in LN

In a scenario where performing job A depends on the result of job B, it is hard to decide at what time job A must be scheduled, and how long job B runs. To handle dependent jobs, you can now create a job group. Use the Job Groups (ttaad5140m000) session to create a job group. A job group has a name, with the same characteristics as a job name, and a description. The Status and User of the job group are handled automatically.

After creating the job group, the jobs are added to the group, approximately in the order the jobs must be performed. The first job in the group (with the lowest Group Number) determines the handling of the whole job group, such as execution date and whether the job group is being repeated. If the job group is not repeating, the job group and all non-repeating jobs in the job group are deleted when the job group has run.

The dependencies of the jobs in the job group are also determined. A job in the job group can only depend on a job in the same job group with a lower job number.

You can use the specific options in the Job Groups (ttaad5140m000 andttams5640m000) sessions to change the status of the job group. The job group statuses have the same meaning as the status of the jobs and the same status changes are allowed.

Note: Job groups are only handled by the BSE service Job Scheduler Service.

Previous Article A/P Payment Update in LX 8.3.4
Next Article If you can't see everything that happens on your shop floor, you are at a competitive disadvantage
Print
37848 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.
First133134135136138140141142Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...