OTTO: How to get started? It’s easy!

The evaluation process for business operations improvements and related software is normally fairly long because it takes time to first understand the software and then to analyze how it will be used. However, how the software works won't truly be understood until it is actually functioning in either a live environment or a simulation of that environment using a reasonably complete test database. 

In order to overcome this challenge we use the following process:

  • Telephone meeting to discuss needs.
  • Webinar to determine common understanding.
  • Load data into OTTO for a live demo.
  • No-obligation trial of the software.

Your only obligation is to supply resources to evaluate OTTO's capabilities. This approach allows you to see exactly how OTTO operates in your specific environment and what benefits you can gain. Several of our customers have actually realized sufficient benefits during the trial-period to justify their purchase of OTTO. Best of all, this evaluation approach offers you extremely low cost and low risk with the potential for high payback in a short period of time.

Previous Article BPCS/LX Tip of the Week: Purchase Order Receive All Processing
Next Article Did you know that when you move to LX 8.4, the 100 series maintenance programs will be performed using ...
Print
24481 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

▪ Four sets of costs: actual, standard, frozen standard, and simulated

▪ Nine user-defined elements per set

▪ Full and partial cost roll-up and simulation

▪ Cumulative in-process cost tracking

▪ Cost summaries by item

▪ Cost definition tied to work centers or material type

▪ Process hour costing

First133134135136138140141142Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last