Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

Shop calendar maintenance, SFC140D1 This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply to a single work center and override any Global or Facility conditions.

If you have deleted a work center in Work Center Maintenance, CAP100D1, you cannot delete its shop calendar. The system treats the work center shop calendar like a global calendar for that year. If you try to delete it, you will delete the global shop calendar for that year.

Range processing provides daily or weekly maintenance of all overrides for a period of up to one year with a single command.

The following explains how Infor LX uses calendars for manufactured and purchased parts planning:

  • Infor LX treats purchased and manufactured parts in the same way.
  • Infor LX does not use the work center calendar.
  • In facility planning, Infor LX uses the facility calendar.
  • If the global calendar has additional days blocked out relative to the facility calendar, MRP/MPS plans consider both the facility and global days-off.


In all cases, the system uses the item master/CIC lead time parameter to determine the release date for the planned order regarding the due date from the forecast or parent demand. The system considers days blocked out in the facility and global calendars when it determines the planned order release date.

Example: Assume the entire system (Global) has a specific date set as a regular workday. If one particular Facility recognizes this day as a holiday, no hours are available on work centers within that facility. If conditions at one work center are an exception to this holiday, that work center can be maintained with its own set of conditions.

Simulation Mode

The Shop Calendar Selection/Maintenance Simulation program, MRP747B, uses the Shop Calendar Maintenance programs, SFC140D, in a simulation mode. The MRP program allows you to maintain shop calendar information to simulate capacity planning and to view the results before you use the data in live capacity planning.

When you run MPS by facility, you cannot maintain global calendars. This safeguard prevents a user from unintentionally overwriting the live global calendar if the user runs Copy to Live, MRP770D.

Access: Menu SFC

Previous Article Infor LX & BPCS Materials Tip: Over-Receipts
Next Article Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)
Print
19120 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

To create and maintain shop orders use SFC500 Shop Order Entry Maintenance. These orders use the standard bill of material (BOM) as the base list of components. You can also set up standard routings, which list the operations,

or work steps, involved in manufacturing.

 

To release shop orders, use the Shop Order Release program, SFC505. Infor ERP LX groups shop orders by user ID for batch processing. Use Shop Packet Print, SFC520, to print the shop orders that you select. SFC530 allows you to create multi-level shop orders to link shop orders together with a common end item parent. Linking multiple shop orders together for a final assembly product provides support for make-to-order and engineer-to-order manufacturing environments which need to schedule these multiple orders together or as a vertical slice in the production schedule.

 

You can make changes to shop orders after you print them. Use Shop Order Entry/Maintenance, SFC500, to update the shop orders. Changes are immediately visible on the inquiry screens for SFC300 and SFC350. To reprint the shop packet, use Reprint Shop Packet, SFC560.

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.


To calculate the offset, the system takes the parent lead time from the Item 
Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.


Note that the offset calculation uses only calendar records that have a blank 
work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program SFC140, in your Shop Floor Control documentation for shop calendar details.

First135136137138140142143144Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: