Baan/LN Tip of the Week: Warehouse Material Movement / Problems With the Inventory Structure Table (whinr150)

This has come up as an issue during various stages of warehouse material movements – transfers, outbounds, shipments. We have seen it right up to 10.4. The inventory structure table (whinr150) becomes a problem. The error points to that table, but users are lost as to how to fix it.

In the session Units by Unit Set many companies let the field Storage default to Yes. If the UOM is not intended to be used in inventory then that setting should be No. 

If an item is purchased in UOM different from the inventory unit and the setting is Yes then LN adds a record in that UOM to the inventory structure table. It is that record that causes problem later.

The session has an option to change the value of the storage field. Specific > Convert Use for Storage. This option works both ways and will correct all inventory in the UOM range. 

Should a user receive an error that references inventory structure table then the solution is to check that session to see if an odd UOM exists in it. If so use the Convert Use for Storage to correct the problem.

Previous Article Baan/LN Tip: Disabling Unused Functionality in LN
Next Article Crossroads is proud to work with Johnson Crushers International on their LN re-implementation to 10.6
Print
36546 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have setup your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are setup and what transactions along with their frequency are captured.

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.
 

  1. If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  2. If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

 

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

 

First136137138139141143144145Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...