Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Anthony Etzel

Anthony Etzel- Featured Speaker at inPower 2019

Infor IDF is replacing green screens for inquiries and release LX 8.4 for file maintenance. This session will show you how to use IDF over your non-LX file. 
 

Many Companies have IDF and are not effectively using it. This session will cover:

  • Building a business object (Intergrator) 
    • How to create a logical expression
    • How to make a field a maintainable field with IDF
  • Views 
    • How to create custom views
    • How to navigate in IDF and create search subsets
Previous Article Pushing Forward In the Face of Adversity. Soundview recently suffered a major loss when fire struck on January 30, 2019.
Next Article Baan/LN Tip: New Mapping Scheme
Print
22641 Rate this article:
4.5
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.
First137138139140142144145146Last

Theme picker

Tips: LN | Baan

Instead of sharing tables through logical linking, you can replicate table content between companies. This approach allows certain non-key attributes of a record to vary by company. For example, if you replicate bills of materials rather than sharing them, each company can associate a different warehouse with the same bill of material. This way, the bills of materials are consistent across companies, while the warehouses can differ.

Replication also enables selective availability of records in other companies. For instance, when replicating items, you might limit which items are available in a sales company based on their item group, only including end items. You can further refine replication to specific subsets, such as particular item groups.

Keep in mind that replication requires any referenced tables to be either replicated or shared as well.