Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Crossroads RMC

We are proud to announce the launch of quarterly Lunch & Learn webinars for BPCS & LX!

  • Have a question about your BPCS/LX system and don’t know where to turn?
  • Want information about the next release of the software?

Crossroads RMC consultants are here to help!

With 250+ BPCS/LX implementations and upgrades under our name, we are the largest BPCS/LX practice in the USA. Spend 30 minutes with us and hear straight-shooting consultants talk about best practices and real-life implementation experiences.

Join us for 30 minutes: 
Watch Video Now


Topics: BPCS 4.0.05CD to LX conversion from a finance point-of-view

  • Understand the benefits of LX 
  • Navigate the transition path developed through client experiences
  • Learn about the capabilities of the Crossroads RMC, LX practice

Previous Article BPCS/LX Tip of the Week: Inventory Period Balance Freeze
Next Article Tip of the Week: Have you defined your KPIs?
Print
27703 Rate this article:
No rating
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.
First137138139140142144145146Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories