Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Anthony Etzel

Save the Date: LX Communities WebEx- Shop Floor Application hosted by Crossroads RMC - March 14, 2017 - 10:00 AM CST

Tuesday, March 14, 2017 - 10:00 a.m. Central

Register Today!

Infor LX Communities Virtual WebEx on Shop Floor Applications
Tuesday, March 14, 2017
10:00 am | Central Standard Time | 1 hr

Attend this conference to discuss: 

  • Problems and concerns with the Shop Floor Application
  • Routing file and Work Center file reviews showing how specific settings can determine the expected outcome for shop floor information
  • Is downtime a big concern? How is downtime captured today? Is downtime considered when setting up capacity parameters?

Crossroads will have a team of seasoned consultants on the call.  This team has been working with the BPCS/LX ERP since the mid 1990’s.

Crossroads RMC has been an Infor partner for 10 years and offers a complete and comprehensive set of software solutions to support manufacturing optimization for companies running on the IBM i platform. Our solutions focus on delivering real-time visibility and control over your entire operation. With over 30 years of experience, Crossroads RMC has become a trusted advisor and technology partner for manufacturers across the globe. 

Previous Article Baan/LN Tip of the Week: Use of Calendars in LN
Next Article How Technology Can Improve Operations & Bring Your Business Closer To Your Customer
Print
25091 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.
First137138139140142144145146Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories