Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Tip of the Week: Gain Efficiency & Save Money - Evaluate Your Production Lines

When is the last time you took a hard look at your production lines?

  • How are we moving product through our facility?
  • Do we have work instructions / drawings available where needed?
  • Do we have frequently used inventory available at the line?
  • Where are the bottlenecks?
  • Are processes automated, where possible?

Taking a hard look at your processes and procedures may reveal some interesting results. Don’t assume that everyone is doing things the same way. Some may be superstars, and others may need some mentoring. Some processes may be outdated and costing you time and money, while others are extremely efficient. One area of the business may benefit from how others operate. Take the time to review and analyze your findings. Your company may benefit greatly as a result.

Optimize Your Manufacturing Today!

Previous Article Supply Chains Need to Turn to the Digital Frontside
Next Article Tip of the Week: Gain Efficiency & Save Money - Evaluate Your Production Lines
Print
42960 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.
First144145146147149151152153Last

Theme picker

Tips: LN | Baan

Instead of sharing tables through logical linking, you can replicate table content between companies. This approach allows certain non-key attributes of a record to vary by company. For example, if you replicate bills of materials rather than sharing them, each company can associate a different warehouse with the same bill of material. This way, the bills of materials are consistent across companies, while the warehouses can differ.

Replication also enables selective availability of records in other companies. For instance, when replicating items, you might limit which items are available in a sales company based on their item group, only including end items. You can further refine replication to specific subsets, such as particular item groups.

Keep in mind that replication requires any referenced tables to be either replicated or shared as well.

12345678910Last

Theme picker

Categories