Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

You may have started your setup of your ERP system one way, and have discovered over time that maybe it no longer fits how you need to do business. Here are some pros/cons to consider for a Multi Finance / Single Logistic setup.

 

Pros/Cons of Multi Finance / Single Logistic Company Set-Up

Pros
Each legal entity can have its own general ledger and balance sheet.
Income statements can be generated for the different enterprise units included in the logistics company.
Centralized operations – purchasing, sales, manufacturing, planning, warehousing, etc.
Logistics data visible to all logistics users – a pro if this is what is desired.
One BOM, Routing, and Cost for each item.

 

Cons
Care must be taken in the set up of integration transactions, sales offices, purchase offices, etc. to insure that financial transactions are posted to the correct financial company.
 
 
Logistics data visible to all logistics users – a con if this is not what is desired.

Previous Article The Industrial IlT: Manufacturing and Supply Chain Visibility, But Better
Next Article BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 3
Print
47427 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.
First144145146147149151152153Last

Theme picker

Tips: LN | Baan

Instead of sharing tables through logical linking, you can replicate table content between companies. This approach allows certain non-key attributes of a record to vary by company. For example, if you replicate bills of materials rather than sharing them, each company can associate a different warehouse with the same bill of material. This way, the bills of materials are consistent across companies, while the warehouses can differ.

Replication also enables selective availability of records in other companies. For instance, when replicating items, you might limit which items are available in a sales company based on their item group, only including end items. You can further refine replication to specific subsets, such as particular item groups.

Keep in mind that replication requires any referenced tables to be either replicated or shared as well.

12345678910Last

Theme picker

Categories