Infor M3 & Movex Tip of the Week: Views & Sorting Orders

One of the most common complaints from M3 users is that the wrong information is displayed on B (list) panels, or it is displayed in the wrong order. M3 provides a tool that allows users to personalize the display so only relevant information is seen without programming assistance from IT.

It is divided into two components:

  1. Views – Defines the column headings or information to be displayed.
  2. Sorting Orders – Defines how the display is organized and presented. It permits the filtering of the above data allowing you to eliminate the display of nonrelevant information.

The tool provides skilled users with the flexibility to retrieve data from within M3 making it more useful and user-friendly.

Previous Article Infor LN & Baan Tip of the Week: Reports to Analyze Company Performance
Next Article M3/Movex Tip of the Week: Year-End
Print
30971 Rate this article:
5.0
Frank Petrasio

Frank PetrasioFrank Petrasio

Other posts by Frank Petrasio

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.
First146147148149151153154155Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: