Infor LN & Baan Tip: Using the “Use Up” Functionality in Infor LN

To use the ‘Use-Up’ or ‘Alternative’ functionality the correct ATP settings of the use-up item must be defined. Order Planning makes use of ATP to determine if there is still supply available. The component needs to have a CTP horizon greater than 0. Then a top down item selection should be chosen when generating order planning in order for the ATP checks to be done and for the system to plan for the correct components.

Selecting the 'top down item' box when generating order planning is essential because when order planning is generated for only the top level item the components aren't "really" planned for. But when a top down selection is run, the system goes through the BOM and plans for each component accordingly.

Previous Article Tim Baker – Infor LX User Group’s Newest Board Member!
Next Article Infor LX & BPCS Period End & Fiscal Year End Processing Checklist
Print
20034 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.
First146147148149151153154155Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: