Infor LN & Baan Tips & Tricks for OPERATIONS: Order Quantity Dependent Routings vs Default Routings

Order quantity-dependent routings

An automatically selected routing tailored to a specific production order quantity is useful. An example would be if the production order quantity is large, a routing with high production rates is used; If the order quantity is small, another routing is selected.

You can set up these quantity-dependent routings:

  • Select the Quantity-dependent Routing check box in the Item - Production (tiipd0101m000) session.
  • Enter the routing codes in the Item - Routings (tirou1101m000) session. Enter the maximum quantity for which a routing is valid in the Up to Quantity field.

Note: If multisite functionality is activated, the routings available may vary per site on the job shop bill of material selected. Differences in routings have an impact on the standard cost calculation.

Default routing

If the Quantity-dependent Routing check box is not selected, the default routing applies to an item. However, this default routing must also be linked to the item. To find out, LN checks the default routing code in the Default Routing field of the Job Shop Master Data Parameters (tirou0100m000) session. Next, LN checks whether the default routing code is linked to the item in the Item - Routings (tirou1101m000) session. If so, the default routing applies to the item. If the default routing is not linked to the item, no routing is used.

Previous Article Infor LX/BPCS Tips & Tricks for OPERATIONS: Track all order holds added & released
Next Article Infor LX/BPCS Tips & Tricks for FINANCE: Default Billing Reason Code from User Order Class
Print
6998 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.
First146147148149151153154155Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories