BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 2

Understanding: How many hours remain in total and at each operation?

Now let’s look at what information is being supplied from the shop floor.

It’s not uncommon for transaction reporting to be captured manually on the shop packet that was issued to the factory floor when the SO was released.

The big question is, is anything done with the data? Is it collected and keyed to a  spreadsheet and not shared, or is the transaction data keyed to SFC600? If it is being keyed, ask how often and by whom? Some companies use alternative methods to capture transaction data that do not require batch keying via a keyboard.

Not a lot of data is required to be keyed to SFC600 in order for the SO Inquiry to be useful. The data that should be reported for the transaction process is as follows:

  • The type of hours being reported – machine, run labor, setup labor
  • If reporting setup and run labor you want an employee clock number
  • The shop order and the operation that is being reported
  • Is the operation complete
  • How many good were produced at this operation
  • How many hours – the numbers of hours are critical. Do the employees estimate how many hours they worked, or do they track actual time started and stopped in order to calculate the actual number of hours.

Based on what is captured and how often will have an impact on the SO inquiry screen. Understanding the batch times as to when the transactions are keyed will provide you with the window as to the SO status at that point in time. Or, are they keyed as they happen in a near real time fashion so that you can have a more current view of the factory floor.

Previous Article Baan/LN Tip of the Week: ERP Setup - Pros & Cons
Next Article Downtime Tips
Print
34697 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.
First146147148149151153154155Last

Theme picker

Tips: LN | Baan

Instead of sharing tables through logical linking, you can replicate table content between companies. This approach allows certain non-key attributes of a record to vary by company. For example, if you replicate bills of materials rather than sharing them, each company can associate a different warehouse with the same bill of material. This way, the bills of materials are consistent across companies, while the warehouses can differ.

Replication also enables selective availability of records in other companies. For instance, when replicating items, you might limit which items are available in a sales company based on their item group, only including end items. You can further refine replication to specific subsets, such as particular item groups.

Keep in mind that replication requires any referenced tables to be either replicated or shared as well.