Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

Shop calendar maintenance, SFC140D1 This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply to a single work center and override any Global or Facility conditions.

If you have deleted a work center in Work Center Maintenance, CAP100D1, you cannot delete its shop calendar. The system treats the work center shop calendar like a global calendar for that year. If you try to delete it, you will delete the global shop calendar for that year.

Range processing provides daily or weekly maintenance of all overrides for a period of up to one year with a single command.

The following explains how Infor LX uses calendars for manufactured and purchased parts planning:

  • Infor LX treats purchased and manufactured parts in the same way.
  • Infor LX does not use the work center calendar.
  • In facility planning, Infor LX uses the facility calendar.
  • If the global calendar has additional days blocked out relative to the facility calendar, MRP/MPS plans consider both the facility and global days-off.


In all cases, the system uses the item master/CIC lead time parameter to determine the release date for the planned order regarding the due date from the forecast or parent demand. The system considers days blocked out in the facility and global calendars when it determines the planned order release date.

Example: Assume the entire system (Global) has a specific date set as a regular workday. If one particular Facility recognizes this day as a holiday, no hours are available on work centers within that facility. If conditions at one work center are an exception to this holiday, that work center can be maintained with its own set of conditions.

Simulation Mode

The Shop Calendar Selection/Maintenance Simulation program, MRP747B, uses the Shop Calendar Maintenance programs, SFC140D, in a simulation mode. The MRP program allows you to maintain shop calendar information to simulate capacity planning and to view the results before you use the data in live capacity planning.

When you run MPS by facility, you cannot maintain global calendars. This safeguard prevents a user from unintentionally overwriting the live global calendar if the user runs Copy to Live, MRP770D.

Access: Menu SFC

Previous Article Infor LX & BPCS Materials Tip: Over-Receipts
Next Article Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)
Print
19014 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding:

The Machine Master File


Machines are associated with a work center. For example, in the work center you may have multiple machines and each machine can have a unique machine ID. If there are several machines that perform the same function, they may operate at different speeds and efficiencies. Setting up the machine master can be a benefit for planning capacity and shop order throughput.

BPCS/LX Tip of the Week: SFC600

In addition to SFC650, this ERPLX program is also used to capture and post shop floor information.

The key difference between the two is that SFC600 only captures Labor (run time) reporting, machine time, downtime and indirect time.

If you use SFC600, then all shop order material receipts and issues would be captured using INV500.

Both Inventory and Shop Floor Transaction entry is keyboard dependent, unless you incorporate an automated method like an MES solution to capture the data.
First149150151152154156157158Last

Theme picker

Tips: LN | Baan

Instead of sharing tables through logical linking, you can replicate table content between companies. This approach allows certain non-key attributes of a record to vary by company. For example, if you replicate bills of materials rather than sharing them, each company can associate a different warehouse with the same bill of material. This way, the bills of materials are consistent across companies, while the warehouses can differ.

Replication also enables selective availability of records in other companies. For instance, when replicating items, you might limit which items are available in a sales company based on their item group, only including end items. You can further refine replication to specific subsets, such as particular item groups.

Keep in mind that replication requires any referenced tables to be either replicated or shared as well.