Infor LN & Baan Tip of the Week: Job Groups in LN

In a scenario where performing job A depends on the result of job B, it is hard to decide at what time job A must be scheduled, and how long job B runs. To handle dependent jobs, you can now create a job group. Use the Job Groups (ttaad5140m000) session to create a job group. A job group has a name, with the same characteristics as a job name, and a description. The Status and User of the job group are handled automatically.

After creating the job group, the jobs are added to the group, approximately in the order the jobs must be performed. The first job in the group (with the lowest Group Number) determines the handling of the whole job group, such as execution date and whether the job group is being repeated. If the job group is not repeating, the job group and all non-repeating jobs in the job group are deleted when the job group has run.

The dependencies of the jobs in the job group are also determined. A job in the job group can only depend on a job in the same job group with a lower job number.

You can use the specific options in the Job Groups (ttaad5140m000 andttams5640m000) sessions to change the status of the job group. The job group statuses have the same meaning as the status of the jobs and the same status changes are allowed.

Note: Job groups are only handled by the BSE service Job Scheduler Service.

Previous Article A/P Payment Update in LX 8.3.4
Next Article If you can't see everything that happens on your shop floor, you are at a competitive disadvantage
Print
40492 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding:

The Machine Master File


Machines are associated with a work center. For example, in the work center you may have multiple machines and each machine can have a unique machine ID. If there are several machines that perform the same function, they may operate at different speeds and efficiencies. Setting up the machine master can be a benefit for planning capacity and shop order throughput.

BPCS/LX Tip of the Week: SFC600

In addition to SFC650, this ERPLX program is also used to capture and post shop floor information.

The key difference between the two is that SFC600 only captures Labor (run time) reporting, machine time, downtime and indirect time.

If you use SFC600, then all shop order material receipts and issues would be captured using INV500.

Both Inventory and Shop Floor Transaction entry is keyboard dependent, unless you incorporate an automated method like an MES solution to capture the data.
First151152153154156158159160Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: