Baan/LN Tip of the Week: Company Calendar

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

Previous Article BPCS/LX Tip of the Week: SFC600 & SFC650
Next Article Infor and Crossroads RMC are proud to offer a joint webinar on Taking Your Shop Floor Paperless - August 28th, 2014.
Print
62895 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.
First152153154155157159160161Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories