Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Crossroads RMC is proud to enter their 21st year in partnership with Paccar for Baan data collection

In 1998, Paccar, Inc. chose Crossroads RMC to be their data collection partner for Baan IV. That partnership has grown over the years and now incorporates almost 200 data collection licenses and 15 different Crossroads applications that run on mobile devices throughout Paccar’s facility. This year, Paccar has elected to extend the Crossroads Data Collection - Web Collect to some of their 3rd party contractors in order to support an increase in production. With the installation of the Crossroads Data Collection - Web Collect, the subcontractors will be able to complete sub-assembly activities and inventory transfers all within Paccar’s Baan system which the subcontractors will be accessing via a point to point solution built for them.

Previous Article Baan / LN Tip of the Week: Analyzing Inventory Adjustments – 10.6
Next Article BPCS / LX Tip of the Week: Inventory Period Balance Freeze
Print
38180 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.
First152153154155157159160161Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last