Infor LN & Baan Tip of the Week: Customer Defined Fields

Customer Defined Fields (CDFs) can be added to tables, screens, reports and BODs and validation and calculation logic can be defined around those fields.

Use the CDF concept to store additional data in the standard Infor LN tables. The CDF definitions are stored separately from the table definitions in the Data Dictionary. For the end user, the CDFs behave in the same way as the standard fields, if defaulting, validations, etc. are built using the CDF logic of the table extension point. The session extension point also has features for the CDFs.

CDFs are configured per package combination. This implies that when moving your companies from one package combination to another, the CDF definitions must be present in the target package combination. Otherwise you lose the data in the CDFs.

Previous Article Crossroads RMC is proud to introduce our new Production Order Variance Reports package for Infor LN
Next Article Infor LN & Baan Consulting News: So we put our hands up, like the ceiling can’t hold us…
Print
42645 Rate this article:
4.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.
First152153154155157159160161Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: