Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt

Hunter Douglas Architectural Products Selects Crossroads RMC for LN 10.6 Upgrade Project

LN Upgrade 10.6

Hunter Douglas, the world leader in window coverings and a major manufacturer of architectural products, has selected Crossroads RMC for their LN 10.2.1 to 10.6 upgrade project. Hunter Douglas has been an LN user for years, but due to a requirement from their parent organization to modernize their hardware/infrastructure, it was decided to update their ERP version as well. Phase 1 of the project will consist of a base technology upgrade with a Phase 2 planned for 2020. Phase 1 Go-Live is slated for January 1, 2020.

To learn more about our Infor LN & Baan Consulting, contact us at: 800.762.2077, email Kathy Barthelt, or visit our Services webpage.

Previous Article Infor LN & Baan Tip of the Week: The Production Bill of Material – 10.7
Next Article Crossroads RMC is proud to partner with an American manufacturer of diagnostic healthcare
Print
27493 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.
First152153154155157159160161Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.