BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
39744 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.
First152153154155157159160161Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: