Baan/LN Tip of the Week: SIC Planning for MRP/MPS Planned Items

If you have a parts warehouse and prefer to use SIC for planning (re-order point) but need to use MRP/MPS planning for production, create a non-nettable warehouse for the parts warehouse and run the SIC plan against that warehouse.

When running the SIC plan, be sure to set the Order System to “MPS to MRP” for Baan IV and to “Planned to Planned” for Baan V and LN.

Using this method you keep the parts inventory out of the production planning and in the hands of the parts warehouse planner.

Previous Article Downtime & Data Loss – How Much Can You Afford?
Next Article BPCS/LX Tip of the Week: Work Center & Machine Locations
Print
54523 Rate this article:
3.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.
First152153154155157159160161Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: